Mandatory inspections are being introduced for all air conditioning systems with rated cooling output greater than 12kW. This includes the combined output of one or more individual air conditioning units in a building.
If your air conditioning system has a rated output greater than 250 kW, you must have had your first inspection by 4th January 2009.
If your air conditioning system has a rated output greater than 12kW, but less than 250kW you must have had your first inspection by 4th January 2011.
For new systems installed on or after 1 January 2008, the first inspection must have taken place within 5 years of the installation date.